=History of Light Combat Aircraft (LCA)=
 
=History of Light Combat Aircraft (LCA)=

Revision as of 02:46, 29 May 2015

This is a collection of articles archived for the excellence of their content.

History of Light Combat Aircraft (LCA)

The Times of India, December 20, 2014

History: LCA

2015:IAF finally receives first series

The Times of India

Jan 18 2015

Chethan Kumar

After a 32-year wait, the Indian Air Force (IAF) received its first series production version of the Light Combat Aircraft Tejas (LCA-SP1). Its induction into a fighting squadron, however, will take longer. The IAF, sources said, is looking to raise the first squadron with a fleet of six to eight LCAs. Given the inadequate number of aircraft, this cannot be done before 2016.

A squadron, according to a retired Air Marshal, generally comprises 18 pilots. It has a service aircraft, a standby platform and a trainer.“However, the number could vary depending on the aircraft and other variables.“

Sources said that neither the SP-1 nor the SP-2 will make it to a fighting squadron; versions from the SP-3 and later will be considered.

Hindustan Aeronautics Limited (HAL) chairman R K Tyagi, however, told STOI: “...The SP-1 has been handed over to the IAF by the defence minister. They have accepted the aircraft. Where but in the squadrons is its place?“ The SP1, which first flew in October 2014, has had only five flights and needs more hours before induction. Also, an initial operational clearance (IOC) configuration without the latest electronic warfare suite, long-range missile capabilities and mid-air refuelling means there may be further improvements required before it is finally in ducted into a squadron.

Saturday's ceremony was only symbolic, according to sources. “India can truly claim the LCA as a success only after the aircraft get commissioned into a squadron,“ the Air Marshal said. The IAF has placed an initial order of 40 aircraft, 20 of which will be in the IOC configuration. HAL can produce eight aircraft a year.

“After the second one reaches the IAF in March, the remaining six will be delivered before March 31, 2016; three out of these six will reach the IAF before June, 2015,“ Tyagi said. The cost of one SPstandard LCA could touch about Rs 160 crore, thanks to the delays; an earlier estimation was about Rs 120 crore.

Defence minister Manohar Parrikar and chief of air staff Air Chief Marshal Arup Raha were in Bengaluru for a meeting of the panel that looks into the progress of LCA. While there was no news on what happened at the closed-door meet, sources said the handing-over ceremony was squeezed into Parrikar's schedule.

2001-15:milestones

The Times of India Jan 19 2015

Chethan Kumar

Over 80 trial flights to test systems cancelled in 2014

As Team Tejas burns the midnight oil to integrate new weapon systems and upgrade other capabilities on the light combat aircraft (LCA) as mandated by the Indian Air Force (IAF), bad weather has taken away many flying hours, critical for testing such systems before certification. From January 4, 2001, when wing commander Rajiv Kothiyal flew the first LCA prototype to January 17, 2015, the day the first aircraft was handed over to the IAF, 2,850 trial flights of LCA have taken place. Notwithstanding the nature of tests each of these flights carry out, ranging from weapon delivery to navigation, trial flights are crucial, senior IAF officials say.

However, Team Tejas was forced to abandon 80 scheduled flights last year, some attempting to even test the Russian Gun integrated with an LCA prototype. IAF has been pressurizing Aero nautical Development Agency (ADA) which has designed LCA to have this feature on the plane.

ADA chief PS Subramanya told TOI, “Last monsoon saw 80 of our trial flights get cancelled, making them fly this year to check its efficiency.“ Without these test flights, ADA cannot guarantee IAF of the performance, nor get certification. In 2014, a total of 350 test flights took place, about 150 less than 2013. “...A few flights also had to be postponed due to technical reasons,“ Subramanya said.

The team, currently working on integrating mid-air refuelling capabilities on Tejas, is looking at achieving more than 500 flights in 2015, with a final operational clearance for LCA expected in 2016.

About 15 LCAs lie in the hangers of HAL, including the seven Limited Series Production (LSP) aircraft, two Technology Demonstrators, three Fighter Prototypes, two Trainer Prototypes and one Naval Prototype.